Overall description
The wind park Trautmannsdorf is located on a hill, basically used for agricultural purposes. The wind turbines are located on premises of the communities Gallbrunn and Stixneusiedl, which are part of the community Trautmannsdorf. Originally 9 wind turbines were planned, but because of ornithological considerations wind turbine number 1 could not be realised. Due to organisational reasons the numeration of the wind turbines still goes from 2 to 9. Close-by is the main city of this district Bruck/Leitha, where another wind park of the “Windpark Bruck/Leitha Gmbh&Co KG” company is located.

---> Homepage of the community Trautmannsdorf (only available in German)
Technical details:
  • 8 wind turbines Vestas V80 2MW

  • Installed capacity: 16 MW

  • Hub hight: 100 m

  • Rotor diameter: 80 m
  • ---> Details of wind park (only available in German)
    ---> Significant project steps - overview for download (42 kB)

    Day of the Wind in the past years in mid-June
    (June 16th, 2010 and June 14th, 2009 and June 30th, 2008 and ......)
    In the past years Raiffeisen-Leasing, IGW, PROFES and the Stixer-winemakers organised a "Wind-Wine-Field-Trip" within the windpark Trautmannsdorf on the global day of the wind. Participants met for hiking, wine tasting, sport and fun and driving E-Mobiles in Stixneusiedl.

    ---> Global wind day - June 15th
    Meeting the minister for environmental affairs Niki Berlakovich
    (October 9th,2009)
    In Stixneusiedl, close to the windpark Trautmannsdorf, representatives of Raiffeisen-Leasing, IG-Windkraft and PROFES met the minister for environmental affaires Berlakovich. He supported the enforced use of wind energy in Austria - for more details please refer to www.igwindkraft.at
    Security practice with fire brigades
    (October 13th, 2006)
    Despite the assumed dangerous date (Friday the 13th) several fire men of Trautmannsdorf, Sarasdorf, Gallbrunn and Berg participated in a security practice organised by PROFES and Vestas. After the successful practice, everybody has been enthusiastic about the sophisticated installation engineering and the very high security standards.
    High civil participation in wind park
    (May 8th, 2006)
    The issuing of a civil participation by Raiffeisen-Leasing has been a great success. More than one million Euro have been subscribed by the inhabitants and the municipality of Trautmannsdorf. Now, all new shareholders are awaiting "windy times".
    Grand opening ceremony at June 3rd, 2005 - a big success
    (June 6th, 2005)
    At Friday, June 3rd, 2005 the official grand opening ceremony of the wind park Trautmannsdorf took place on the wind park area. The emony was conducted by the member of the provincial government DI Plank and blessed by the saffragan bishop DDr. Krätzl whereas the social program offered various dishes and entertaining amusements. Additionally the wind-wine-lane was opened by PROFES.
    All 8 wind energy plants in operation
    (December 14th, 2004)
    Despite a very windy month VESTAS assembling team could finish the construction of all wind energy plants under great effort in November 2004. The initial operation was conducted in no time by sometimes 5 teams working at the same time resulting in a full capacity operating wind park (16 MW).
    Assembling finished
    (November 27th, 2004)
    The assembling of the whole wind park Trautmannsdorf, the necessary infrastructure like lanes and cabling,could be finished with the installation of wind energy plant No. 9. after only a 3 month construction period. This success can be attributed to a very accurate planning and the ambitious collaboration of all companies
    - sincere thanks are given to all!
    Construction of the first wind energy plant
    (November 1st, 2004)
    After the completion of the wind energy plant No. 2 at Oct. 29th, 2004 the rotor turbine could be fixed at All Saint´s Day Eve - the whole assembling of wind energy plant No. 3 could be done in one single day, causing surprise to numerous watchers.
    Ground breaking ceremony
    (October 6th, 2004)
    The ground breaking ceremony of wind park Trautmannsdorf took place at Oct. 10th, 2004, after a long-standing planning period. That happened under a large attendance of great personalities from politics, press, public officials, planning responsibilities, citizens, and the project financier Raiffeisen-Leasing. Additionally the entertainment program took place at the pavilion next to the wind energy plant No. 9.
    All permissions become legally binding
    (September 9th, 2004)
    The environmental impact assessment could be issued after the completion of the ornothological expertise lasting one year. Consequently all necessary permissions for the wind park assembling were available at Sept. 9th. 2004. Immediately, the assembling kick off was given.